Brickell Bay Drive’s waterfront has been the subject of years of planning, community discussion, and resilience studies. Now, as the City moves toward construction, residents need a clear picture of what is changing and how it will affect their neighborhood.

The Brickell Bay Drive Seawall & Resiliency Improvements project combines shoreline protection with a renewed Baywalk, roadway work, drainage improvements, and landscaping. It covers the waterfront between SE 14th Street and SE 15th Road.

WHERE THE PROJECT STANDS

The City’s November 2026 update reports that 60% structural plans were approved with notes on November 9, with 90% structural plans expected in December. Construction is currently estimated for March 2027 through November 2028. These dates remain subject to change.

Read the City’s project update

THE LONG VIEW

Years in the making.

The project’s roots reach back to the years following Hurricane Irma. In September 2017, storm surge overtopped the aging seawall, highlighting the need for stronger shoreline protection.

During then-Commissioner Ken Russell’s tenure, Brickell Bay Drive became part of the discussion about how Miami should invest in resilience. His District 2 office’s December 2018 overview described $1 million in Miami Forever Bond funding for planning and design. That was an early design allocation, rather than the construction budget for the full project now being developed.

An August 2018 Resilience Accelerator workshop expanded the vision to consider public access, green space, the environment, and neighborhood connectivity alongside flood protection. Resilient305 later described Brickell Bay Drive as a demonstration project that could inform waterfront standards elsewhere in Miami.

Irma exposes the vulnerability

Storm surge overtops the waterfront barrier along Brickell Bay Drive.

A broader waterfront vision

The August Resilience Accelerator workshop expands the approach. In December, Ken Russell’s office describes $1 million for planning and design.

Design enters the capital plan

The City includes a funded design-criteria package covering seawall reconstruction and a linear park.

Residents help shape the project

A December 13 meeting at Simpson Park gathers input on the waterfront, roadway, drainage, and pedestrian connections.

Designs return to the community

A March 19 meeting at Emerald at Brickell presents the design and renderings and gathers further feedback.

A design-build agreement

The City Clerk’s records identify the agreement with Magnum Construction Management dated November 19.

CURRENT STAGE

Engineering advances

EXP announces its design role in March. The City reports progress on the structural plans in November.

Construction target

The City currently estimates construction from March 2027 to November 2028. This schedule may change.

Timeline sources are linked in the documents section below.

UNDERSTANDING THE DESIGN

How much higher
will the seawall be?

The publicly presented design calls for a seawall crest at 8.0 feet NAVD88. The City’s earlier survey information placed the existing crest at approximately 4.2 feet NAVD88. That is a difference of approximately 3.8 feet, or about 3 feet, 10 inches. EXP’s March 2026 announcement repeats those figures.

SEAWALL CREST ELEVATIONS Same surveying reference: NAVD88
Earlier crest
4.2 ft
Proposed crest
8.0 ft

Approximate increase: 3.8 feet

The eight-foot figure is an elevation, not the wall’s height above the walkway. NAVD88 is a surveying reference. What pedestrians see depends on the difference between the seawall crest and the finished walking surface.

Updated cross-sections should show the wall, Baywalk, road, and neighboring entrances together. Those drawings would make the effects on views, accessibility, and building connections much easier to understand.

City streetscape rendering showing the proposed sidewalk, roadway and landscaped strip
Roadway and streetscape concept · City of Miami / Tetra Tech, March 2024. View the original presentation slide.

EXP describes a linear greenway for pedestrians and cyclists, roadway reconstruction, and drainage improvements. Its description includes a soil-cell system beneath the sidewalk intended to support drainage and tree growth. The waterfront, street, and drainage infrastructure need to work together.

FOR CONDOMINIUM COMMUNITIES

What does this mean
for private seawalls?

Miami adopted Ordinance No. 13980 on March 25, 2021, updating waterfront construction and maintenance provisions. The published code sets a six-foot NAVD88 minimum for applicable shoreline protection outside the Miami River and its tributaries. Permit applications must also demonstrate the ability to raise improvements incrementally, including at least two feet above minimum elevations, through 2070.

The code provisions reviewed do not establish an automatic requirement for every neighboring condominium to match the City’s proposed eight-foot elevation simply because this public project is proceeding.

The code does establish circumstances that can require private improvements. An association’s responsibilities depend on its own property and work:

New construction and substantial improvements

Applicable elevation and design requirements can be triggered by new construction or substantial improvements to a property.

Substantial seawall repairs

The threshold includes repairs affecting at least 50% of a wall’s length, costing at least 50% of a replacement wall, or changing the elevation along at least 50% of its length. Compliance can be required along the property’s shoreline.

Maintenance and flooding violations

Owners must maintain their shoreline protection and prevent tidal water from passing through or over their property onto neighboring property or public rights-of-way. Violations can require corrective work. The code’s definition of tidal waters excludes storm-surge extremes as the test for an existing structure’s maintenance compliance.

The code provides a variance process for certain site constraints and alternative protective designs. Approval is conditional and does not remove the responsibility to protect neighboring properties and public streets.

At the County level, Ordinance 25-73, approved July 1, 2025, separately revised seawall and bulkhead permitting procedures and processing requirements. It concerns permitting and should not be described as a blanket eight-foot seawall mandate for Brickell condos.

What boards should establish

Who owns the seawall, its current elevation and condition, whether planned repairs trigger the code, and how the City’s improvements will connect to the property. A building’s engineer and legal counsel should evaluate those facts with the City.

THE RESIDENT PERSPECTIVE

Clear plans.
Clear responsibilities.

As the design advances, residents should have documented answers to the questions that affect everyday life, access, and their buildings.

How will the new elevations meet existing buildings?

Updated drawings should identify seawall, sidewalk, roadway, and entrance elevations at adjoining properties, including connections between public and private shorelines.

How will rainfall drain from lower properties?

Residents should be able to review the drainage analysis and understand how rainfall will leave existing buildings and low areas after construction.

Will any condominium need related work?

The City should identify any affected associations, the legal basis for required improvements, the timing, and who is responsible. The materials reviewed do not establish building-specific obligations.

What happens to access, parking, and traffic?

The construction plan should explain building and emergency access, deliveries, pedestrian routes, accessibility, parking changes, and the sequence of street closures.

Who will fund and maintain each component?

Residents need a complete funding breakdown and clear responsibility for maintenance after the seawall, landscaping, Baywalk, and drainage work is completed.

When will residents see the updated plans?

A further public review should show what changed from the 2024 presentation and provide a meaningful opportunity for questions before construction.

After nearly a decade of discussion, residents should be able to see how this investment will protect the neighborhood and how it will function at their own front doors.

FOLLOW THE PUBLIC RECORD

Sources & documents

Information reviewed November 23, 2026. The renderings illustrate the March 2024 presentation; the latest stamped construction plans have not been reviewed.